SOCOTEC Italia has started testing and testing activities on materials at the Garigliano Nuclear Power Plant, the activities come within the scope of the decommissioning carried out by SOGIN SpA.

Specifically, the activities fall on the following test areas:

  • Laboratory tests on hardened concrete
  • Laboratory tests on C.A. steels and C.A.P.
  • Laboratory tests on rolled steels
  • Analysis of materials to be disposed of
  • Non-destructive testing of welds
  • On-site services Georadar surveys
  • Tightening torque verification
  • Load tests on poles